Concrete Patio Calculator
To pour a 12 × 16 ft patio at 4 inches thick you need about 2.37 cubic yards of concrete plus 10% waste — roughly 118 bags of 80 lb mix, though ready-mix delivery is usually cheaper at that size.
Figures based on the sources listed belowUpdated How we calculate
Buy 118 bags.
Buy 118 bags
2.37 cu yd + 10% waste = 2.61 cu yd
Low
$531.00
Expected
$708.00
High
$944.00
Includes 0.24 cu yd waste
How this number is calculated
2.37 cu yd + 10% waste = 2.61 cu yd ÷ 0.0222 cu yd per bag = 118 bags
Next step in your project
- Gravel Calculator
A compacted gravel base under the patio. Opens with your 12 × 16 ft filled in.
2.6 cu yd — ~26% of a standard truck load
Bagged vs. Ready-mix delivery
Bagged (80 lb bags)
118 bags
$531.00–$944.00 (typ. $708.00)
Ready-mix delivery
2.6 cu yd
$365.04–$521.48 (typ. $430.22)
For ~2.6 cu yd, ready-mix delivery is usually cheaper and far less labor.
When can I walk on it?
- Forms off, light foot traffic24–48 hours
- Normal foot traffic and furniture7 days
- Full design strength28 days
Typical waits for ordinary concrete mix kept moist and above 50 °F (10 °C). They vary with the mix, temperature and curing: cold weather adds days, and fast-setting mixes shorten some waits. Follow the bag or your supplier.
Shopping list
- 80 lb concrete mix
- Mixing tub
- Finishing trowel
- Rebar
- Concrete sealer
- Concrete edger
Your project
- Patio length × patio width: 12 × 16 ft
- Thickness: 4 in
- Waste: Standard (10%)
Also pick up
- 80 lb concrete mix
- Mixing tub
- Finishing trowel
- Rebar
- Concrete sealer
- Concrete edger
Reopen this calculation: /calculators/concrete-patio/?s=eyJyb29tIjp7Imxlbmd0aEZ0IjoxMiwid2lkdGhGdCI6MTZ9LCJkZWR1Y3Rpb25zIjpbXSwid2FzdGVQY3QiOjAuMSwicGFyYW1zIjp7InRoaWNrbmVzc0luY2hlcyI6NH19
Show diagram
Saved projects
No saved projects yet.
Concrete curing timeline
| Milestone | Typical wait | Example: poured Sat, Oct 3 |
|---|---|---|
| Forms off, light foot traffic | 24–48 hours | Sun, Oct 4 – Mon, Oct 5 |
| Normal foot traffic and furniture | 7 days | Sat, Oct 10 |
| Full design strength | 28 days | Sat, Oct 31 |
Methodology & assumptions
Volume is calculated as patio length × width × (thickness in inches ÷ 12), then divided by 27 to convert cubic feet to cubic yards. A waste percentage is added for spillage and uneven subgrade, and the result is divided by the coverage per bag (about 0.0222 cu yd for an 80 lb bag) and rounded up to the next whole bag. Because patios often exceed 1 cubic yard, ready-mix delivery is frequently the more economical and practical option. The curing timeline under the calculator uses typical published waits, cited below; they vary with the mix, temperature and curing.
- Manufacturer bag-yield specs (80 lb ≈ 0.60 cu ft)
- Typical US ready-mix and bag price ranges, 2026
- American Concrete Institute, ACI 308R guide to curing concrete: keep concrete moist for at least the first 7 days (ordinary portland cement mixes)
- Portland Cement Association, Design and Control of Concrete Mixtures: moisture and temperature drive strength gain, which slows in cold weather; design strength is commonly specified at 28 days
- Concrete Network, How Long Before You Can Drive on New Concrete?
How to calculate how much concrete you need for a patio
- Measure your patio area. Measure the length and width of the patio in feet to find its footprint.
- Set the slab thickness. Enter the slab thickness in inches — 4 inches is standard for a patio slab.
- Add waste. Add 10% for a standard pour, or 5% if you are confident in your forms and mix estimate.
- Divide by bag coverage and round up. Divide the total volume (with waste) by the coverage per bag (about 0.0222 cu yd for an 80 lb bag) and round up to the next whole bag. For volumes over about 1 cubic yard, price out ready-mix delivery too.
Worked examples
| Project | Result |
|---|---|
| 12 × 16 ft patio, 4 in thick, standard waste | 2.37 cu yd + 10% waste ≈ 2.61 cu yd → 118 bags |
| 10 × 20 ft patio, 4 in thick, minimal waste | 2.47 cu yd + 5% waste ≈ 2.59 cu yd → 117 bags |
| 14 × 14 ft patio, 4 in thick, standard waste | 2.42 cu yd + 10% waste ≈ 2.66 cu yd → 120 bags |
Frequently asked questions
- How much concrete do I need for a patio?
- Multiply the patio length by width in feet, multiply by the thickness in feet (inches divided by 12), then divide by 27 to convert cubic feet to cubic yards. Add 10% for waste, then divide by the coverage per bag (about 0.0222 cu yd for an 80 lb bag) and round up.
- How many bags of concrete are in a cubic yard?
- About 45 bags of 80 lb mix per cubic yard, since each bag yields roughly 0.60 cu ft and a cubic yard is 27 cu ft. A 60 lb bag yields about 0.45 cu ft (around 60 bags per cubic yard), and a 40 lb bag yields about 0.30 cu ft (around 90 bags per cubic yard). For a patio, that means a 12 ft by 10 ft patio 4 in thick (40 cu ft, about 1.5 cu yd) needs roughly 67 bags of 80 lb mix before waste.
- Is bagged concrete or ready-mix delivery cheaper for a patio?
- Most patios need well over 1 cubic yard once you multiply out length, width, and thickness — at that volume, ready-mix delivered by truck is usually cheaper per yard and dramatically less labor than mixing dozens of bags by hand. Bagged mix is more practical for small patios, repairs, or footings under about 1 cubic yard.
- Do I need control joints or a gravel base for a patio slab?
- Yes for both, though neither changes the concrete volume this calculator estimates. A compacted gravel base (typically 4 in.) improves drainage and reduces cracking, and control joints cut every 8-10 ft limit where cracks form as the slab cures and shifts with temperature.
- Should I round up or down when figuring out how many bags to buy?
- Always round up to a full bag. Running short mid-pour is a serious problem with concrete since it starts setting once mixed — cold joints from a delayed second batch would weaken the patio. For a 12 ft by 10 ft patio 4 in thick, 44 cu ft with 10% waste is 73.3 bags of 80 lb mix, so buy 74.
- How long before you can walk on concrete?
- For a patio: typically 24 to 48 hours for light foot traffic, once the surface is hard enough not to scuff; edge forms usually come off around the same time. Wait about 7 days before normal traffic, furniture or a loaded wheelbarrow. Poured on Sat, Oct 3, that is Sun, Oct 4 – Mon, Oct 5 for light foot traffic and Sat, Oct 10 for normal use. These are typical figures for ordinary concrete mix kept moist and above 50 °F (10 °C); cold weather slows curing and adds days, so follow the bag or your supplier.
- How long does concrete take to cure?
- For a patio: concrete sets in hours but keeps curing, gaining strength, for weeks. Typical planning figures: 24–48 hours for light foot traffic, about 7 days before normal use or loads, and full design strength at 28 days. Poured on Sat, Oct 3, that is Sun, Oct 4 – Mon, Oct 5, Sat, Oct 10 and Sat, Oct 31; it keeps hardening slowly after that. Keep it moist for at least the first 7 days (mist it, or cover it with plastic or a curing compound) and protect it from freezing: moisture and warmth are what let it reach its strength. Below about 50 °F (10 °C) curing slows, so plan on more days.
Guides
Handy tools
- Slope Calculator: A patio slab is poured with about 1/4 inch of fall per foot for drainage: find the drop across the width of your patio.