A 12 × 8 ft hole dug 3 ft deep is 10.67 cu yd bank (in place): 12 × 8 × 3 = 288 cu ft, or 10.67 cu yd in the ground. Once dug, common earth swells by about 25%, so there are 13.33 cu yd of loose soil to move, which is 2 loads in a 10 cu yd truck. Pick the shape, enter the size and depth, choose the soil and your truck size, and the calculator gives the in-place volume, the loose volume and the loads. Call 811 before you dig.
Figures based on the sources listed belowUpdated How we calculate
10.67 cu yd bank (in place).
10.67 cu yd bank (in place)
- Loose volume after swell: 13.33 cu yd, at 25% swell (common earth or loam)
- Truck loads to haul: 2 loads (truck holds 10 cu yd)
- Weight: not estimated for this soil: it varies a lot with moisture, so ask your hauler or the dump site
Shopping list
- Round point shovel
- Trenching shovel
- Contractor wheelbarrow
- Marking paint (upside-down can)
- Tape measure (100 ft)
- Tarp (for the spoil pile)
Your project
- Length (top of hole) × width (top of hole): 12 × 8 ft
- Shape: Rectangle, straight sides (length × width × depth)
- Depth: 36 in
- Soil type (sets the swell): Common earth or loam: 25% (range 15–30%)
- Truck or trailer capacity: 10 cu yd
Also pick up
- Round point shovel
- Trenching shovel
- Contractor wheelbarrow
- Marking paint (upside-down can)
- Tape measure (100 ft)
- Tarp (for the spoil pile)
Reopen this calculation: /calculators/excavation/?s=eyJyb29tIjp7Imxlbmd0aEZ0IjoxMiwid2lkdGhGdCI6OH0sImRlZHVjdGlvbnMiOltdLCJ3YXN0ZVBjdCI6MC4xLCJwYXJhbXMiOnsic2hhcGUiOjAsImRpYW1ldGVySW4iOjM2LCJjb3VudCI6MSwidGhpY2tuZXNzSW5jaGVzIjozNiwiYm90dG9tTGVuZ3RoRnQiOjgsImJvdHRvbVdpZHRoRnQiOjQsInNvaWwiOjEsImN1c3RvbVN3ZWxsUGN0IjoyNSwidHJ1Y2tDdVlkIjoxMH19
Show diagram
Saved projects
No saved projects yet.
Bank and loose cubic yards for common holes and trenches
| Project | Bank | Loose: sand | Loose: common | Loose: clay | Loose: rock |
|---|---|---|---|---|---|
| Utility or drain trench, 1 × 100 ft, 3 ft deep | 11.11 | 12.78 | 13.89 | 14.44 | 17.78 |
| Footing trench, 2 × 60 ft, 3 ft deep | 13.33 | 15.33 | 16.67 | 17.33 | 21.33 |
| Footing trench, 2 × 120 ft, 4 ft deep | 35.56 | 40.89 | 44.44 | 46.22 | 56.89 |
| 12 post holes, 12 in round × 42 in deep | 1.22 | 1.40 | 1.53 | 1.59 | 1.95 |
| Pond or hot tub pit, 8 × 8 ft, 2 ft deep | 4.74 | 5.45 | 5.93 | 6.16 | 7.59 |
| Pool, 12 × 24 ft, 5 ft deep | 53.33 | 61.33 | 66.67 | 69.33 | 85.33 |
| Pool, 16 × 32 ft, 5 ft deep | 94.81 | 109.04 | 118.52 | 123.26 | 151.70 |
| Pool, 16 × 32 ft, 8 ft deep | 151.70 | 174.46 | 189.63 | 197.21 | 242.73 |
Swell by soil type
| Soil | Published range | Used here | Loose per bank | Cu yd loose per 1 bank |
|---|---|---|---|---|
| Sand or gravel | 10–18% | 15% | 1.15 | 1.15 |
| Common earth or loam | 15–30% | 25% | 1.25 | 1.25 |
| Clay | 20–40% | 30% | 1.3 | 1.30 |
| Rock (blasted or broken) | 40–80% | 60% | 1.6 | 1.60 |
Truck loads by truck size
| Project | 2 cu yd | 10 cu yd | 12 cu yd | 14 cu yd |
|---|---|---|---|---|
| Footing trench, 2 × 60 ft, 3 ft deep | 9 | 2 | 2 | 2 |
| Footing trench, 2 × 120 ft, 4 ft deep | 23 | 5 | 4 | 4 |
| 12 post holes, 12 in round × 42 in deep | 1 | 1 | 1 | 1 |
| Pond or hot tub pit, 8 × 8 ft, 2 ft deep | 3 | 1 | 1 | 1 |
| Pool, 12 × 24 ft, 5 ft deep | 34 | 7 | 6 | 5 |
| Pool, 16 × 32 ft, 5 ft deep | 60 | 12 | 10 | 9 |
Methodology & assumptions
Bank volume is the volume of the hole as it sits in the ground, which is how earthwork is measured. Rectangle: length × width × depth. Round: π × (diameter ÷ 2)² × depth × the number of holes. Sloped sides: for a hole whose walls slope evenly from a top opening to a smaller floor, the prismoidal formula V = depth ÷ 6 × (A top + 4 × A mid + A bottom) is exact, where A top = top length × top width, A bottom = bottom length × bottom width and A mid is the area halfway down, ((top length + bottom length) ÷ 2) × ((top width + bottom width) ÷ 2). It covers a trench with sloped sides and a pyramid-shaped pit. For a 14 × 10 ft top, 10 × 6 ft floor and 4 ft depth that is 14.42 cu yd, against 20.74 cu yd for a straight-sided 14 × 10 ft hole of the same depth. Enter depth, top and floor sizes as measured; cubic feet ÷ 27 = cubic yards, and 1 cu yd = 0.7646 m³. Swell: dug soil takes up more room than it did in the ground, because it is loosened and fills with air. Loose volume = bank volume × (1 + swell %). Published tables disagree on the exact figure and with good reason: it depends on the soil, its moisture and how it is dug. So each soil type here carries the range reported by the sources below (sand or gravel 10–18%, common earth or loam 15–30%, clay 20–40%, rock 40–80%) and the calculator uses the middle of the range, rounded to the nearest 5% (15%, 25%, 30%, 60%). That middle value is this page’s choice, an estimate, not a published figure; the handbook point values quoted by the sources (about 12% for sand and gravel, 25% for loam, 40% for clay, 65% for well-blasted rock) all fall inside the ranges. Laboratory measurements of clays and silts can come in higher still, so choose Custom and type your own figure if you know it. Loads = loose volume ÷ the truck or trailer capacity you enter, rounded up; the truck figure is yours because it varies (a tandem-axle dump truck is typically 10–14 cu yd, a full-size pickup bed roughly 2 cu yd, both rules of thumb) and a load of dirt can reach the legal weight limit before the box is full, so check the weight with the hauler. Weight is shown only for sand and gravel, as loose cubic yards × 1.4 tons per cubic yard, the density the gravel calculator on this site uses; it is approximate. No density is given for other soils, since it changes too much with moisture. Not included: working room around forms or a pool shell, topsoil you strip off first, backfill and compaction (compacted soil can end up smaller than its bank volume), and soil that is reused on site. The metric toggle shows lengths in m, depth and diameter in cm and volumes in m³.
- Caterpillar, Earthwork Volumes Reference Tables (cat.com article reproducing material weights, swell and load factors from the Caterpillar Performance Handbook): loose and bank weights and load factors by material, for example dry sand and gravel at about 2,900 lb per loose cu yd. Could not be opened from the build environment; figures checked against search-result excerpts, so confirm on the page
- Engineering ToolBox, Soil and Rock - Bulking Factors: swell ranges by material (clay about 20–40%, loam about 15–25%, earth about 20–30%, rock about 40–80%) with the worked example of 300 m³ of clay at 40% becoming 420 m³ in the dump. Checked through search-result excerpts, not the full page
- Project Engineer, Swell Factors for Various Soils: handbook-style point values (sand 12%, gravel 12%, earth or loam 25%, clay 40%, well-blasted rock 65%) that the ranges above enclose. Checked through search-result excerpts, not the full page
- Zanco Journal of Pure and Applied Sciences, Swell and Shrinkage Percentages for Various Soil Types and their Prediction from Intrinsic Soil Properties: laboratory measurements, with higher and wider swell for clays, silts and gravels than the handbook tables (the reason the swell is user-editable)
- HomeGuide, Dump Truck Sizes: Types, Dimensions & Capacity Guide: tandem-axle dump trucks typically hold 10 to 14 cubic yards (a rule of thumb; use your hauler’s figure)
- OSHA, Trench and Excavation Safety fact sheet (29 CFR 1926 Subpart P): a protective system (sloping, shoring or a trench box) is required in excavations 5 feet (1.5 m) or deeper unless the excavation is in stable rock, and a competent person decides below that depth; OSHA’s rules cover work sites, but the hazard is the same in a yard
- 811 Call Before You Dig (811beforeyoudig.com): 811 is the national number to have buried utilities marked before any digging; waiting periods and rules are set by each state, so check yours
- Gravel calculator on this site: the 1.4 tons per cubic yard used for the sand and gravel weight line. Prismoidal formula: standard solid geometry (exact for a solid whose cross-section changes linearly with depth)
How to estimate the dirt to remove from a hole or trench
- Call 811. Before you dig, call 811 (the US call-before-you-dig number) or your local one-call service so buried lines are marked.
- Measure the hole. Measure the length, width and depth of the hole or trench, or the diameter and depth of a round hole. For sloped sides, measure the opening at the top and the floor at the bottom.
- Calculate the bank volume. Length × width × depth in feet, divided by 27, gives cubic yards in the ground. For round or sloped holes use π × r² × depth or the prismoidal formula.
- Add the swell. Multiply by 1 plus the swell for your soil (about 1.25 for common earth) to get the loose volume you will have to move.
- Count the loads. Divide the loose volume by the truck or trailer capacity and round up. Ask the hauler for their capacity and weight limit.
Worked examples
| Project | Result |
|---|---|
| 12 × 8 ft hole, 3 ft deep, common earth, 10 cu yd truck | 10.67 cu yd bank (in place), 13.33 cu yd loose at 25% swell, 2 loads |
| Footing trench, 2 ft wide × 60 ft long × 3 ft deep, common earth | 13.33 cu yd bank (in place), 16.67 cu yd loose, 2 loads in a 10 cu yd truck |
| 12 post holes, 12 in round × 42 in deep, sand or gravel | 1.22 cu yd bank (in place), 1.40 cu yd loose at 15% swell, 1 load |
| Sloped pit: 14 × 10 ft top, 10 × 6 ft floor, 4 ft deep, common earth | 14.42 cu yd bank (in place), 18.02 cu yd loose, 2 loads in a 10 cu yd truck |
| 12 × 24 ft pool hole, 5 ft deep, clay, 12 cu yd truck | 53.33 cu yd bank (in place), 69.33 cu yd loose at 30% swell, 6 loads |
| The 12 × 8 × 3 ft hole with a custom 45% swell | 10.67 cu yd bank (in place), 15.47 cu yd loose, 2 loads |
Frequently asked questions
- How do I calculate how much dirt I need to remove?
- Multiply length × width × depth, all in feet, to get cubic feet, then divide by 27 for cubic yards. A 12 × 8 ft hole 3 ft deep is 288 cu ft ÷ 27 = 10.67 cu yd in place. That is the bank volume. The soil you dig up takes more room, so also add the swell: at 25% for common earth that is 13.33 cu yd loose, which is 2 loads in a 10 cu yd truck. For a round hole use π × radius² × depth, and for a trench with sloped sides the prismoidal formula in the methodology.
- What is the difference between bank, loose and compacted volume?
- Bank volume (also called in-place or "bank cubic yards") is the soil in the ground. Loose volume is the same soil once it has been dug and is sitting in a pile or a truck, larger by the swell. Compacted volume is the soil after it is tamped back down as fill, which can be smaller than the bank volume. Hauling is priced and loaded by loose volume; the size of the hole is measured by bank volume.
- How much does soil swell when you dig it?
- It depends on the soil, so this calculator works from a range for each type: sand or gravel 10–18%, common earth or loam 15–30%, clay 20–40%, rock (blasted or broken) 40–80%. It uses the middle of the range, rounded to 5%: 15%, 25%, 30%, 60%. Sources disagree on the exact figures, wet or clumpy soil swells more, and lab measurements of clay can run higher, so treat the result as an estimate and pick Custom to enter your own swell. A 45% custom swell on the 12 × 8 × 3 ft hole gives 15.47 cu yd loose and 2 loads.
- How many truck loads of dirt do I need to haul away?
- Loose volume ÷ truck capacity, rounded up. The default hole has 13.33 cu yd of loose soil: 2 loads in a 10 cu yd truck. A tandem-axle dump truck is typically 10–14 cu yd; a full-size pickup bed holds roughly 2 cu yd, so the same soil is many more trips (see the table). Both are rules of thumb, so use your hauler’s figure. Soil is heavy, and a load can reach the weight limit before the box is full: ask the hauler how much they will take per trip.
- How do I find the volume of a hole with sloped sides?
- Use the prismoidal formula: depth ÷ 6 × (top area + 4 × mid-depth area + bottom area), where the mid-depth area uses the average of the top and bottom lengths and the average of the top and bottom widths. It is exact when the walls slope evenly. A 14 × 10 ft top, 10 × 6 ft floor and 4 ft depth: 4 ÷ 6 × (140 + 4 × 96 + 60) = 389.3 cu ft = 14.42 cu yd, less than the 20.74 cu yd of a straight-sided 14 × 10 ft hole. Choose "Rectangle with sloped sides" and enter the top size as length and width and the floor under bottom length and width.
- How much dirt does a swimming pool excavation produce?
- Start with the pool’s length × width × depth. A 12 × 24 ft pool dug 5 ft deep is 53.33 cu yd in the ground and, in clay at 30% swell, 69.33 cu yd loose, 6 loads in a 12 cu yd truck. The real excavation is bigger than the water: it has to take in the pool walls, the base and working room, and a deep end makes the hole deeper than the average depth, so add those dimensions to the hole you enter or ask the installer for their numbers. See also the pool volume calculator for the gallons.
- Do I need to call before I dig?
- Yes. In the US, 811 is the national number to call before any digging, even a small hole, so the buried gas, power, water and telecom lines get marked. The call is free, and each state sets how many days before you dig you must make it, so check your state’s 811 center. Wait for the markings, and hand-dig carefully near them. Outside the US, ask your local utilities or the national one-call service.
- How deep is it safe to dig a trench?
- Trench walls can collapse with no warning, and a cave-in can bury a person. OSHA’s excavation rules (29 CFR 1926 Subpart P), which apply to work sites, require a protective system, such as sloping the sides, shoring or a trench box, for excavations 5 feet (1.5 m) deep or more unless they are in stable rock, and have a competent person decide on shallower ones. They are a good guide for any digging: do not work in a deep trench, keep spoil piles back from the edge, and get a professional for anything deep.
- Is the volume for backfill the same as the volume removed?
- No. Fill that is compacted back into the hole is not the same as the loose soil you dug. Soil placed and compacted in layers can end up smaller than the bank volume it came from, and if you remove material such as a footing, pipe or a pool shell, there is less to put back. This calculator is for what you dig out and haul; use the gravel, topsoil or footing calculators for what goes back.
- Can I estimate the weight of the dirt?
- Only roughly. For sand and gravel the calculator multiplies the loose cubic yards by 1.4 tons per cubic yard, the density used by the gravel calculator on this site. Other soils vary a lot with moisture and are not estimated; ask your hauler or the dump site, since they usually charge by the load or the ton. Wet soil can be much heavier than dry.
Handy tools
- Feet and Inches Calculator: Turn a tape reading in feet and inches into the decimal feet the length and width fields take.
- Cubic Yards to Tons: Convert the loose cubic yards to tons once you know the density of your soil.