Concrete Mix Ratio Calculator: Cement, Sand, Gravel and Water
A 10 × 10 ft slab 4 in thick (1.24 cu yd, or 1.36 cu yd with 10% waste) mixed 1:2:3 needs 10 bags of 94 lb cement (about 9.4 cu ft), 18.8 cu ft of sand, 28.2 cu ft of gravel and about 53 gallons of water at a water-cement ratio of 0.5. The same job in 80 lb pre-mix bags is 62 bags. The dry parts add up to about 1.54 times the mixed volume (a typical estimate), because the sand fills the gaps between the gravel and the cement fills the gaps in the sand.
Figures based on the sources listed belowUpdated How we calculate
Buy 10 bags.
Buy 10 bags
1.23 cu yd + 10% waste = 1.36 cu yd
- Sand: 18.8 cu ft (≈ 0.94 tons)
- Gravel: 28.2 cu ft (≈ 1.46 tons)
- Water (at the water-cement ratio): 53 gal
- Sand and gravel by the yard: 1.74 cu yd
- Pre-mix instead (80 lb bags): 62 bags (≈ 4,960 lb)
Low
$120.00
Expected
$160.00
High
$220.00
Includes 0.12 cu yd waste
How this number is calculated
1.23 cu yd + 10% waste = 1.36 cu yd ÷ 0.144 cu yd per bag = 10 bags
1.4 cu yd — ~14% of a standard truck load
Bagged vs. Ready-mix delivery
Bagged (80 lb bags)
62 bags
$279.00–$496.00 (typ. $372.00)
Ready-mix delivery
1.4 cu yd
$190.12–$271.60 (typ. $224.07)
For ~1.4 cu yd, ready-mix delivery is usually cheaper and far less labor.
Shopping list
- 94 lb Portland cement
- Mixing tub
- Portable concrete mixer
- Contractor wheelbarrow
- Mixing hoe
- Finishing trowel
Your project
- Length × width: 10 × 10 ft
- Mix by volume: 1:2:3 concrete (cement : sand : gravel)
- Depth: 4 in
- Or type a volume: 0 cu ft
- Water-cement ratio: 0.5
- Cement bag: 94 lb US bag (1 cu ft)
- Dry-volume factor (optional): 0
- Waste: Standard (10%)
Also pick up
- 94 lb Portland cement
- Mixing tub
- Portable concrete mixer
- Contractor wheelbarrow
- Mixing hoe
- Finishing trowel
Reopen this calculation: /calculators/concrete-mix-ratio/?s=eyJyb29tIjp7Imxlbmd0aEZ0IjoxMCwid2lkdGhGdCI6MTB9LCJkZWR1Y3Rpb25zIjpbXSwid2FzdGVQY3QiOjAuMSwicGFyYW1zIjp7Im1peCI6MSwidGhpY2tuZXNzSW5jaGVzIjo0LCJ2b2x1bWVDdUZ0IjowLCJ3YXRlckNlbWVudFJhdGlvIjowLjUsImJhZ1R5cGUiOjAsImRyeUZhY3RvciI6MH19
Show diagram
Saved projects
No saved projects yet.
Materials per cubic yard by mix
| Mix | Cement (cu ft) | Sand (cu ft) | Gravel (cu ft) | Water (gal) | Loose dry volume (cu yd) |
|---|---|---|---|---|---|
| 1:2:3 concrete | 6.9 (7 bags) | 13.9 | 20.8 | 39.1 | 1.54 |
| 1:2:4 concrete | 5.9 (6 bags) | 11.9 | 23.8 | 33.5 | 1.54 |
| 1:3 mortar | 8.8 (9 bags) | 26.3 | none | 49.5 | 1.3 |
| 1:4 mortar | 7 (8 bags) | 28.1 | none | 39.6 | 1.3 |
| 1:6 mortar | 5 (6 bags) | 30.1 | none | 28.3 | 1.3 |
1:2:3 concrete for common pour sizes
| Pour | 94 lb cement bags | Sand (cu ft) | Gravel (cu ft) | Water (gal) | 80 lb pre-mix bags |
|---|---|---|---|---|---|
| 3 cu ft | 1 | 1.7 | 2.5 | 4.8 | 6 |
| 5 cu ft | 2 | 2.8 | 4.2 | 8 | 10 |
| 10 cu ft | 3 | 5.6 | 8.5 | 15.9 | 19 |
| 20 cu ft | 6 | 11.3 | 16.9 | 31.8 | 37 |
| 27 cu ft | 8 | 15.2 | 22.9 | 43 | 50 |
| 54 cu ft | 16 | 30.5 | 45.7 | 85.9 | 100 |
Water per bag of cement
| Water-cement ratio | Gallons per 94 lb bag | Litres per 50 kg bag |
|---|---|---|
| 0.40 | 4.5 | 20 |
| 0.45 | 5.1 | 22.5 |
| 0.50 | 5.6 | 25 |
| 0.55 | 6.2 | 27.5 |
| 0.60 | 6.8 | 30 |
Methodology & assumptions
The mixed (wet) volume is length × width × depth, or the volume you type, plus the waste you pick. The dry volume of loose materials is that volume × the dry-volume factor: about 1.54 for concrete and about 1.3 for mortar. These are typical estimating figures, not code values (1.27 to 1.33 is quoted for mortar, and 1.52 to 1.57 for concrete), and the box lets you enter your own. The dry volume is shared out by the mix parts: for 1:2:3 the parts total 6, so cement is 1/6, sand 2/6 and gravel 3/6 of it. Cement bags are the cement volume ÷ the bag volume (a 94 lb US bag is taken as 1 cu ft; a 50 kg bag is about 110 lb, so about 1.17 cu ft), rounded up. Water is the water-cement ratio × the cement weight (94 lb per cu ft), divided by 8.34 lb per US gallon. Sand and gravel tons use the site’s planning densities, 1.35 and 1.4 tons per cu yd. Real sand and gravel vary with moisture and grading: wet sand bulks up and carries its own water, so measure a trial batch and adjust. These are volume ratios for small jobs; structural work needs a proper mix design.
- Quikrete Portland Cement data sheet: 94 lb (42.6 kg) bags; concrete proportioned by volume as 1 part cement, 2 parts sand (ASTM C33) and 3 parts gravel (ASTM C33)
- Portland Cement Association, Design and Control of Concrete Mixtures (EB001): the water-cement ratio governs strength and durability, lower ratios giving stronger, less permeable concrete; a bag of cement is 94 lb
- ASTM C270, Standard Specification for Mortar for Unit Masonry: proportions by volume of cementitious materials and sand (sand 2 1/4 to 3 times the cementitious volume)
- ASTM C33, Standard Specification for Concrete Aggregates (the sand and gravel grading the Quikrete data sheet names)
- Quikrete Concrete Mix (No. 1101) data sheet: 80 lb ≈ 0.60 cu ft of concrete
- Dry-volume factors of about 1.54 (concrete) and 1.27 to 1.33 (mortar) are common estimating figures from construction estimating guides, not code values (estimate)
- Typical US retail price of a 94 lb bag of Portland cement, 2026 (estimate)
How to work out cement, sand, gravel and water for a concrete mix
- Find the volume. Multiply length × width × depth in feet (depth in inches ÷ 12) for cubic feet, then add 5 to 10% for waste. Or type the volume if you already have it. 27 cu ft make 1 cu yd.
- Pick the mix. 1:2:3 is the usual general-purpose concrete, 1:2:4 is leaner. For mortar use 1:3, 1:4 or 1:6 cement to sand.
- Convert to dry volume. Multiply the mixed volume by the dry-volume factor, about 1.54 for concrete and 1.3 for mortar (typical estimates).
- Share it out by the parts. Divide the dry volume by the sum of the parts (6 for 1:2:3) and multiply by each part. That gives cement, sand and gravel in cubic feet.
- Turn it into bags and water. Divide the cement by 1 cu ft per 94 lb bag and round up. Water in gallons = water-cement ratio × cement pounds ÷ 8.34. Compare with pre-mix bags before you buy.
Worked examples
| Project | Result |
|---|---|
| 10 × 10 ft slab, 4 in thick, 1:2:3, 94 lb cement bags, 10% waste | 10 bags of cement, 18.8 cu ft sand, 28.2 cu ft gravel, 53 gal water (versus 62 pre-mix bags) |
| 12 × 12 ft patio, 4 in thick, 1:2:4, 10% waste | 12 bags of cement, 23.2 cu ft sand, 46.5 cu ft gravel |
| 5 cu ft of 1:4 mortar (typed volume), 10% waste | 2 bags of cement, 5.7 cu ft sand, 8.1 gal water |
| 10 × 10 ft slab, 4 in thick, 1:2:3 with 50 kg cement bags | 9 bags of cement (50 kg), the same sand and gravel |
Frequently asked questions
- What does a 1:2:3 concrete mix mean?
- One part cement, two parts sand and three parts gravel (coarse aggregate), measured by volume with the same bucket or box. Quikrete’s Portland cement data sheet gives it as the proportion for concrete from bagged cement, sand and gravel. A 1:2:4 mix has one more part of gravel: a little leaner, cheaper and easier to place, and somewhat weaker.
- How much cement, sand and gravel for 1 cubic yard of concrete?
- At the typical dry-volume factor of 1.54, a cubic yard of 1:2:3 takes 6.9 cu ft of cement (7 bags of 94 lb), 13.9 cu ft of sand and 20.8 cu ft of gravel, plus about 39.1 gallons of water at a ratio of 0.5. A cubic yard of 1:2:4 takes 5.9 cu ft of cement (6 bags), 11.9 cu ft of sand and 23.8 cu ft of gravel. Add waste on top.
- What is the dry-volume factor, and why 1.54?
- Loose sand, gravel and cement take up more room than the concrete they make: the cement and sand fill the gaps between the gravel particles, and water and compaction close the rest. Estimators therefore multiply the wet (finished) volume by a factor to get the dry volume of materials to batch. About 1.54 is the usual figure for concrete and 1.27 to 1.33 for mortar, so the calculator uses 1.3 for mortar. These are typical estimates, not code values; the real figure shifts with grading, moisture and how loosely the materials are measured. If your trial batches come out short or long, enter your own factor.
- What water-cement ratio should I use?
- The water-cement ratio is the weight of water divided by the weight of cement. Lower ratios give stronger, less permeable concrete, but a stiffer mix that is harder to place. Around 0.45 to 0.6 is a typical range for site-mixed concrete, with 0.5 a common starting point. The Portland Cement Association’s Design and Control of Concrete Mixtures sets lower maximums for concrete exposed to freezing and thawing or de-icing salts, so use a lower ratio and a proper mix design there. Add water a little at a time: sand that is already damp needs less than the calculator shows.
- How many gallons of water per bag of cement?
- Water per bag = ratio × 94 lb ÷ 8.34 lb per gallon. At 0.45 that is 5.1 gallons per 94 lb bag, at 0.5 it is 5.6 and at 0.6 it is 6.8. For a 50 kg bag, multiply the ratio by 50 to get litres. The water table on this page has the rows in between.
- Why does Quikrete say 5 to 6 bags per cubic yard when this shows more?
- Quikrete’s data sheet gives a yield of roughly five to six 94 lb bags of Portland cement per cubic yard, depending on the proportions and materials used. At the typical dry-volume factor, 1:2:3 comes to 6.9 bags per cubic yard and 1:2:4 to 5.9, at or above the top of that range, so the tool errs towards enough cement. The sheet’s range depends on the sand and gravel used, and the factor is only a typical figure: if your trial batches yield more per bag, enter a lower dry-volume factor to match, and treat the result as an estimate to confirm with a trial batch.
- What mortar mix ratio should I use?
- Cement and sand mortars by volume run from 1:3 (rich, strong, sticky) through 1:4 to 1:6 (lean, workable, weaker). Lean mixes suit rendering and non-structural bedding; richer ones suit paving bedding and repairs. ASTM C270 sets mortar for unit masonry by type, in cement, lime and sand proportions, with sand about 2 1/4 to 3 times the volume of the cementitious materials, so for load-bearing brick and block follow the mortar type your plans call for rather than a plain cement and sand ratio. For 5 cu ft of mortar at 1:4 with 10% waste, this calculator gives 2 bags of cement and 5.7 cu ft of sand.
- Is it cheaper to mix my own concrete or buy pre-mix bags?
- For small pours, bags are less work and nothing is left over: 62 bags of 80 lb mix for the 10 × 10 ft slab, against 10 bags of cement plus 18.8 cu ft of sand and 28.2 cu ft of gravel to buy, haul and measure. Mixing your own starts to pay when you need a lot of concrete, you can buy sand and gravel in bulk, and you have a mixer or the help to batch it. Past about a cubic yard, ready-mix delivery usually beats both. See the concrete bag calculator for the bag count, with 60 and 40 lb sizes.
- Can I use a 50 kg bag of cement?
- Yes: pick it under Cement bag. A 50 kg bag weighs about 110 lb, so at the same density it holds about 1.17 cu ft instead of 1. The 1:2:3 slab then needs 9 bags instead of 10, and the sand, gravel and water are unchanged.
- Is a volume mix strong enough for a slab or footing?
- A 1:2:3 mix is a classic general-purpose proportion, but a volume ratio does not control strength by itself: the water-cement ratio, the grading and cleanliness of the sand and gravel, and curing all matter, and the result varies from batch to batch. For driveways, footings, structural elements or anywhere your building department requires a strength, use ready-mix or a bagged mix with a stated strength, and follow your local code and engineer.